Holy Shrines
Karbala International Airport project proceeds at fast pace
The engineering staff of Karbala International Airport has stated that 80% of the project of building the runway has been achieved.
The engineering staff of Karbala International Airport has stated that 80% of the project of building the runway has been achieved.
They have just begun to build the pillars of the watchtower, and the work is proceeding at a fast pace.
Mohammed Sa’eed, engineer at Teeba Company, has stated that all the work of the terminal has been achieved.