Karbala International Airport project proceeds at fast pace
![](https://shiawaves.com/english/wp-content/uploads/sites/4/2017/07/images_2017_07_20_01.jpg)
The engineering staff of Karbala International Airport has stated that 80% of the project of building the runway has been achieved.
The engineering staff of Karbala International Airport has stated that 80% of the project of building the runway has been achieved.
They have just begun to build the pillars of the watchtower, and the work is proceeding at a fast pace.
Mohammed Sa’eed, engineer at Teeba Company, has stated that all the work of the terminal has been achieved.